The impact of design approach and contracting practices on cost and execution period of school buildings

Abdullatif A. AlMunifi, Ibrahim Abdullah Alameri


DOI: https://doi.org/10.20528/cjsmec.2019.03.002

Abstract


More than two million school-age children in Yemen are unable to enroll in education because of a shortage of school buildings. This is one of the reasons the country missed the Millennium Development Goal of achieving Education for all by 2015. The struggle to afford school accommodation will continue, because of the lack of resources and high unit cost. Construction cost as time schedule for an identical school building vary by the implementing agency. This paper aims to study in-depth this multi-dimensional issue to find out the factors that lead to this variation, as well as the reasons for the high unit cost and lengthy periods of construction. To achieve this objective, comprehensive raw data that was resourced from agencies that are assigned to implement the largest part of the construction program along with data collected through questionnaires and semi-structured interviews were utilized. Complete sets of design and contracting documents of representative schools were used for deeper analysis and evaluation. The analysis shows that the employed design approaches lead to large structural elements and consequently to longer implementation period and 30% increase in cost. It also shows that contractors add up to 20% for the client’s procurement procedure, approvals, and payment cycle. Additionally, bidders price risks related to accessibility to building sites, availability of building materials, and how trouble-prone is the region. The findings are of relevance to researchers, education planners, and practitioners as they are of high importance to policy makers and financiers whose main concern is to meet the growing need for school accommodation.


Keywords


design and procurement practices; bid and risk-based pricing; out-of-school children; Yemen

Full Text:

PDF

References


AL-kohlani M (2009). An investigation of the causes and extent of delay and cost overrun in school construction projects in Yemen. M.Sc. thesis, Bartlett School of Graduate Studies- University College London, UK.

AlMunifi A (1997). Lessons learned from Yemen earthquakes - engineering and environmental aspects. 29th General Assembly of IASPEI. Thessaloniki, Greece.

AlMunifi A (2004). The vision of the Ministry of Education: Programs and policies. The Pre-appraisal Workshop for the Preparation of the Basic Education Development Project. Sana’a, Yemen.

Brown G (2013). Accelerating progress to 2015-Yemen. A Report Series to the UN Special Envoy for Global Education.

Choudhry R, Gabriel HF, Khan MK, Azhar S (2017). Causes of discrepancies between design and construction in the Pakistan construction industry. Journal of Construction in Developing Countries, 22(2), 1–18.

Döring C (2010). Cross-Sector and Multi-Institutional Assessments Study on School Construction Costs in Yemen. The Proceedings of the 13th Architecture & Behaviour Colloquium. Lausanne, Switzerland.

Dosumu OS (2018). Perceived effects of prevalent errors in contract documents on construction projects. Construction Economics and Building, 18(1), 1–26.

Fast Track Initiative (2004). Yemen experience with the fast track initiative. Fast Track Initiative Partnership Meeting. Brasilia.

GET German Education and Training (2008). School Construction Costs in Yemen. Sana’a, Yemen.

Government of Yemen (2018). Yemen Constitution. retrieved from http://www.yemen.gov.ye/. Jan 2019.

Günhan S, Arditi D, Doyle J (2007). Avoiding change orders in public school construction. Journal of Professional Issues in Engineering Education and Practice, 133(1), 67–73.

Khan Q, Chase S (2003). Yemen and the Millennium Development Goals. Working Paper Series. The World Bank.

Laryea S, Hughes W (2008). How contractors price risk in bids: Theory and practice, Construction Management and Economics, 26(9), 911–924.

Ministry of Education (2003). Analysis of the school construction 1996-2003. Sana’a, Yemen.

Ministry of Education (2004). Preparation of the school construction plans and policies.

Ministry of Education (2013). Yemen Education Sector Plan-Mid Term Results Framework 2013-2015.

National Information Center (2018). Law No. (23) for the year 2007 regarding tenders and auctions. https://www.yemen-nic.info/db/laws_ye/detail.php?ID=15594, Jan. 2019.

Ogawa K (2004). Achieving education for all in Yemen: Assessment and current status. Journal of International Cooperation Studies, 12, 2.

Oyeyipo O, Odusami KT, Ojelabi RA, Afolabi AO (2016). Factors affecting contractors' bidding decisions for construction projects in Nigeria. Journal of Construction in Developing Countries, 21(2), 21–35.

PWP (2018). Contracting procedures. Retrieved from www.pwpyemen.org/index.php/en/. Jan. 2019.

SFD (2018). Contracting procedures. The World Bank (2013). Report No: 72143-YE. Project Appraisal Document. Retrieved from www.sfd-yemen.org. Jan. 2019.

The World Bank (1999). Republic of Yemen-Education Sector Assistance Strategy. Human Development Sector.

The World Bank and the Republic of Yemen (2010). Education Status Report. Challenges and Opportunities. A joint publication of the International Bank of Reconstruction and Development.

The World Bank and Yemen Government (2005). Review of civil works components in four education projects. Mission Report.

UNICEF (2018). If not in school - The paths children cross in Yemen. Report.

Vincent M, Monkkonen P (2010). The impact of state regulations on the costs of public school construction. Journal of Education Finance, 35(4), 313–330.

Zaghloul R, Hartman F (2003). Construction contracts: The cost of mistrust. International Journal of Project Management, 21(6), 419–424.


Refbacks

  • There are currently no refbacks.